|
EPRI
- East Kentucky Power Cooperative Polymer Failure Investigation
Paul
Dolloff, PE
"When
Andrew told me that one of our units that we removed from service
failed in EPRI's new 230kV aging chamber test after only one month's
time, I knew EKPC had avoided an outage and our decision to remove
all of our high risk polymer insulators from critical lines was
correct" said Dr. Paul Dolloff, research engineer at EKPC.
"With our newly purchased DayCor corona camera and the inspection
techniques learned from EPRI (Guide to Visual Inspection
of NCI, and Guide to Corona and Arcing Inspections of Overhead
transmission Lines), Dr. Dolloff added, "EKPC will begin
an in-house DayCor II inspection program designed to identify
and remove in-service, high-risk NCI
Early
DayCor II inspection and testing helped EKPC to identify and
remove high-risk polymer insulators from service, preventing catastrophic
failures and thereby avoiding unscheduled outages.
Challenge
Between
1996 and 1998 East Kentucky Power Cooperative (EKPC) experienced
six failures of polymer insulators over a range of voltage levels
shown in the table below. Late in 1999, with a large number of similar
units still in service over a wide range of voltage levels, some
of them on key transmission lines while others serving critical
loads, EKPC contacted EPRI researchers to determine whether the
remaining units were at a high risk of failure and to develop a
plan of action.
Approach
EKPC decided to replace all polymer insulators
of similar design and manufacture from key transmission lines and
radial lines servicing critical customers. One of such a key transmission
line was a 138 kV line that fed the Inland Container Paperboard
and Packing Inc., a large industrial customer with a 50MW load.
EKPC
sent to EPRI a number of units that failed, for analysis. EPRI researchers
of the research center in Lenox MA, led by Dr. Andrew Philips, identified
the failure modes and their causes, and claimed that the principal
cause of the failures was moisture in the internal fiberglass rod
that penetrated through the end fitting. When this happens, either
acid builds up and threatens the integrity of the fiberglass rod
(i.e. mechanical failure), or the moisture tracks up the rod electrically
shortening the NCI until flash under occurs (i.e. electrical
failure). Realizing there was a potential problem with similar units
that remained in service, EKPC contracted EPRI to perform a three-day
on-site inspection with the DayCor camera. After the inspection,
EKPC removed from service 30 units that EPRI had identified as high-risk
and sent them to the EPRI Lenox Center for evaluation. EPRI staff
dissected and analyzed the units, revealing that in over 90% of
the cases moisture penetrated the end fittings. These findings led
EPRI to conclude that similar units remaining in service should
be considered high-risk.
EKPC
decided to replace all polymer insulators of similar design and
manufacture from key transmission lines and radial lines servicing
critical customers. One of such a key transmission line was a 138
kV line that fed the Inland Container Paperboard and Packing Inc.,
a large industrial customer with a 50MW load.
All polymer insulators removed from this line were sent to EPRI
for further evaluation and use in other EPRI-sponsored research
projects. Seven of these units were installed in the 230kV Accelerated
Aging Test that was initiated in January 2001. After only one month
in the aging chamber, one of the units failed electrically in a
manner similar to that observed previously in the field. It is certain
that this unit would have failed in-service; hence, EKPC avoided
an unscheduled outage. --up>
|